Testing for the Selected Modules and Test Report
The following tests at appropriate testing laboratory, will be performed to randomly selected modules from all plant with IEC standards.
– “Power at STC and spectral response measurement (Uncertainty: 1.6 %)
– “Electroluminescence images”.
– “Light induced degradation (LID)”.
– “Power rating”.
– “Performance at low irradiation”.
– “Detailed visual inspection”.
– “Potential induced degradation (PID) test”.
– “Thermal cycling test”.
– “Snail track susceptibility test”.
Schedule
The Report will be provided within 2 weeks after delivery of the modules to the laboratory.